An early start to work today to get ahead of the forecast heatwave, and that will be the story of the week as the heat remains. It was a good day and there now only 2 joists to cut and fit. These ones are around the position of our compostable toilet and I'm just not confident that I have all of the dimensions right yet. I imagine Treebeard in my ear saying "don't be hasty". Tempting to just whack them on though!
Before we move on to flooring we need to do a few things - put in
noggins between the joists to stabilize them and then get the
electrician to have a look at things to see if he needs to get in there
before the flooring goes on. We still haven't finalised which
insulation we will use under the floor, that's something I'm deciding
on now.
It has been odd not having Tarsh around for the day after
all our hours on the weekend together. She is the master of systems.
I am great at using systems when I know how they work but Tarsh
knows how to be clever about processes that astounds me. It sped
things up and clarified our approach to our work. Fantastic!